How to Implement Last Planner® Pull Planning
How to Implement Last Planner® Pull Planning
If you are looking for proven methods to implement Last Planner System® pull planning, here are implementation techniques our Coaches have field-tested on over 100 projects and several hundred sessions, for dozens of companies.
PREREQUISITES
PREREQUISITES
PREREQUISITES
1. Get Executive buy-in to the Last Planner System®. Otherwise, it’s an “experiment” and without solid, vocal executive buy-in the effort will often peter out.
2. Make sure the project Superintendent(s) are in agreement to use the Last Planner method of planning and scheduling since they are the key person(s) in a successful superintendent. It’s a GO-NO GO gate. If the Superintendent says “No”, it’s NO.
3. Get a coach. You wouldn’t send your kids on any playing field – regardless of the sport – without a coach who knows the process, the rules and can patiently train and “coach” the team.
4. Clarify the participants:
GETTING STARTED
GETTING STARTED
GETTING STARTED
Introducing the entire Last Planner System (and Pull Planning) in design and construction on a project (whether new or in progress) requires an initial 2-session foundation of training (that can be done in one day):
LAUNCH THE PLANNING
LAUNCH THE PLANNING
LAUNCH THE PLANNING
Once the team has been trained, our recommended introduction and implementation of Last Planner® specific to the project includes the following: